A flyover under construction in the bustling city of Kolkata collapsed on to moving traffic below, killing at least 14 people with as many as 150 people feared trapped, police said on
Thursday. The 2.2 km-long Vivekananda Road flyover is a project undertaken by the Kolkata Metropolitan Development Authority (KMDA) which was nearing completion, almost 9 years after the
project was undertaken. Television visuals showed residents using their bare hands to try rescue people pinned under a 100-metre (110-yard) length of metal and cement that snapped off at
one end and came crashing down in a teeming commercial district near Girish Park. Here’s everything you need to know about the under-construction flyover: * It was a Rs 164-crore project
which the Left front government initiated in 2007 to ease out traffic in Burrabazar-Posta area and for faster and better movement of Howrah-bound vehicles from north Kolkata. * Immediately
after construction started in 2009, work stopped as the implementing agency, Hyderabad-based IVRCL, faced bankruptcy. * They restarted the work after a gap of a year-and-a-half when the
company managed to arrange for funds through debt restructuring. * Funds were made available to IVRCL — the implementing agency of the Vivekananda Road flyover – under the Jawaharlal Nehru
National Urban Renewal Mission (JnNURM) scheme before the project took off in 2009. * Construction began in February 2009 and the deadline for the inauguration was set at August 2011. * The
2.2km-long flyover has missed nine deadlines since construction started in 2009. * The project got delayed due to various reasons. The design of the flyover was one of them. It had to be
changed several times. * Several residents also went to court seeking a stay order over objections to the flyover’s proximity to several houses. * Two land issues further delayed the
project- one at the Howrah bridge end and the other at the Nimtolla Ghat Street. * For quite some time, land clearance from Kolkata Port Trust to use a patch of land for the Girish
Park-bound ramp was pending. However, CM Mamata Banerjee’s reportedly intervened, helping resolve the dispute and construction work had begun in full swing again. * Chief minister Mamata
Banerjee had instructed authorities to complete the project by February-end of this year. However, it had not met this deadline as well.
Trending News
Want to improve your memory and focus? Try thisExercise isn’t just for your body — your mind can benefit from a good workout too. And research shows that learning anot...
Canada, brazil — but not china — will be hit hardest by trump's steel tariffsCanada and Brazil are likely to bear the brunt of any tariffs on steel imposed by President Donald Trump, according to a...
Non-eu citizen visiting rules ‘more restrictive’ in spain than france_Article published 31 July, 2023_ Second-home owners in France report struggles with the EU’s 90/180-day rule but in Spa...
Page Not Found很抱歉,你所访问的页面已不存在了。 如有疑问,请电邮[email protected] 你仍然可选择浏览首页或以下栏目内容 : 新闻 生活 娱乐 财经 体育 视频 播客 新报业媒体有限公司版权所有(公司登记号:202120748H)...
Coronavirus is not only a medical and economic challenge, but a moral one | thearticleWhile coronavirus poses intractable medical challenges, and the persistence of the lockdown raises the spectre of econom...
Latests News
Here’s everything you need to know about the under-construction flyover that collapsed in kolkata - scoopwhoopA flyover under construction in the bustling city of Kolkata collapsed on to moving traffic below, killing at least 14 p...
Where should I send a statement of England Hockey's account? | FAQsFAQ.SEARCHHEADING Back Useful Contacts Where should I send a statement of England Hockey's account? Please email finance...
Quadrant Minimal | designboom.comDESIGNER'S OWN WORDS: the goal was to design the most minimal door handle possible. this developed into one design ...
Just a moment...WABE’s mission is simple: “Inform, inspire, reflect and empower our greater Atlanta community. ” We do that through the ...
Educare preschools aim to close academic gapsAs teachers rock babies in their arms, a sense of calm settles over a classroom in a bright, modern building on a side s...