Recently completed elevated deck at Kandivali. | FPJ MUMBAI: Kandivali station’s long-awaited improvement work is making steady progress, with the project now at 50% completion. The
overhaul, which is expected to be finished by December 2025, is aimed at modernizing the station and enhancing commuter experience in one of Mumbai’s bustling suburban hubs. The Rs 55 crore
project, spearheaded by the Mumbai Rail Vikas Corporation (MRVC), is part of a larger initiative to upgrade 18 suburban stations across the Mumbai Metropolitan Region (MMR), including key
stations on the Central, Harbour, and Western lines. Stations like Ghatkopar, Vikhroli, Bhandup, Mulund, Dombivli, Neral, and Kasara on the Central line, GTB Nagar, Chembur, Govandi, and
Mankhurd on the Harbour line, and Khar, Kandivali, Nallasopara, Vasai Road, Mira Road, Santacruz, and Bhayander on the Western line are undergoing significant upgrades as part of this
massive transformation, with an estimated cost of around Rs 950 crores. According to MRVC, Kandivali station improvement project includes the construction of new and upgraded infrastructure
designed to ease congestion and improve accessibility. The work comprises a variety of components, such as a 263-meter long deck connecting the South and North FOBs, A South FOB of 40 meters
by 10 meters, A North FOB measuring 84 meters by 6 meters, A Middle FOB of 42 meters by 4 meters, Seven new staircases, three lifts, and four escalators, A new station building on the west
side, Platform 1 widening and additional facilities, including a north-side toilet block, A skywalk of 4.0 meters wide connecting the new South FOB to the existing South FOB on Platforms 2,
3, and 4. "Several key components of the project have already been completed including A 45-meter long elevated deck, 10.4 meters wide, has been installed on Platform 1, complete with
escalators for improved access. Additionally, the South FOB, measuring 40 meters in length and 10 meters in width, along with three staircases on Platforms 1, 2/3, and 4, has been
successfully commissioned" said an official. While significant progress has been made, several elements are still under construction. These include a 197-meter stretch of the deck
between grids C8 and C17, the North FOB, additional lifts (two more), three more staircases, three escalators, the skywalk on Platforms 2/3 and 4, and the north-side toilet block. Once
completed, the upgrade promises to significantly enhance the commuter experience at Kandivali station, alleviating congestion, improving connectivity, and making the station more accessible.
The project’s comprehensive scope, including wider platforms, additional staircases, lifts, and escalators, is expected to handle the growing passenger traffic in the coming years. “Once
the project is finished, it promises to significantly improve commuter experience by reducing congestion and enhancing overall connectivity at Kandivli station,” said an official overseeing
the project.
Trending News
Grieving Parents Honor Their Late Son in Emotional Photo: 'He Was the Angel Holding Us Together'Jason Hahn is a former Human Interest and Sports Reporter for PEOPLE. He started at PEOPLE's Los Angeles Bureau as a wri...
Towards the intermediate band | Nature PhotonicsBy tailoring the electronic band structure of highly mismatched alloys, researchers have shown clear evidence of the exi...
S zeko v the university of the west of england and others: 1405457/2020 and othersS ZEKO V THE UNIVERSITY OF THE WEST OF ENGLAND AND OTHERS: 1405457/2020 AND OTHERS Employment Tribunal decision. Read th...
Ms V Atherton v Ensign Communications Ltd: 2405544/2018 - GOV.UKMs V Atherton v Ensign Communications Ltd: 2405544/2018 Employment Tribunal decision. From: HM Courts & Tribunals Servic...
SXSW: ‘The Guest,’ ‘Oculus,’ ’13 Sins’ Among Midnighters; Full Shorts Slate UnveiledThe final wave of programming set to unspool at SXSW next month will include Midnighter selections The Guest, starring D...
Latests News
Mumbai: kandivali station improvement project reaches 50% completion, set for 2025 completionRecently completed elevated deck at Kandivali. | FPJ MUMBAI: Kandivali station’s long-awaited improvement work is making...
Tottenham 0-1 newcastle as it happened: joelinton strike seals itTOTTENHAM HOTSPUR SQUAD ARRIVES FOR NEWCASTLE LEAGUE GAME TOTTENHAM 0-1 NEWCASTLE * Joelinton seals three points with fi...
John mahoney dead: frasier actor kelsey grammer on eddieFrasier actor John Mahoney has died aged 77, his agent announced yesterday. The star played Martin “Marty” Crane, the fa...
Safety and security - south sudan travel adviceForeign travel advice SOUTH SUDAN ! WARNING FCDO ADVISES AGAINST ALL TRAVEL TO SOUTH SUDAN. CONTENTS * Warnings and insu...
Joseph boakai elected president of liberia, final results showJoseph Boakai elected president of Liberia, final results show | WTVB | 1590 AM · 95.5 FM | The Voice of Branch County C...