How to deal with builder delays to your property in france
How to deal with builder delays to your property in france"
- Select a language for the TTS:
- UK English Female
- UK English Male
- US English Female
- US English Male
- Australian Female
- Australian Male
- Language selected: (auto detect) - EN
Play all audios:
DO YOU RECEIVE THE CONNEXION'S FREE WEEKDAY NEWSLETTER? Sign up here Post-pandemic, it was not uncommon in many parts of the country for builders to issue estimates for projects, the
legally binding devis, with a start date two years in the future. A shortage of skilled tradespeople has compounded problems – French training programmes have for years struggled to attract
plumbers, electricians and masons. With order books still full, and many building projects further delayed by the exceptionally wet winter, hold-ups are likely to continue. While a devis is
legally binding for the builder on aspects such as price, it is also legally binding for the client. Simply saying that you have changed your mind because of the delay could lead to
problems. If the date on the devis has passed, the first thing to do is discuss the problem with the builder. Try to find out the reason for the delay, and when they think they will be able
to start. Good builders are hard to find, and presumably you chose the one you did because you know they work well, so it would be a pity to immediately start threatening legal recourse.
Read more: Man does not have to pay for renovations as no quote signed in France THE ART OF NEGOTIATION If you are able to negotiate a new start date, all the better. Note that the start
date on a devis does not have to be a specific time and date. Builders can legally say that the work will start in a particular quarter of a year. If you are not successful, you could try to
enforce penalties for delays on the builder. With small building firms, this may not go down well, but if it is a large building company it might be an option. In the eye of the law, a
retard travaux is any passing of the delivery date, which should be stated on the devis or contract you signed. After 30 days have passed, you can ask for a court order imposing penalties
for the delay. The standard penalty is one thousandth of the price on the devis for every day’s delay, unless it is a new house being built, in which case the penalty rises to three
thousandths of the price on the devis. Exceptions are if the builder can argue that the delay is caused by you – usually because you have not paid the deposit demanded in the devis. And
other reasons they can point to is if you asked for extra work, not included in the original devis. Bad weather is another valid excuse for work not being completed on time. Simple autumn
rain or summer showers do not fall under this umbrella, but in cases such as last winter, when many building sites were so muddy that machines could not enter, it is a legitimate reason.
Read more: Couple cannot demolish and rebuild French home even if not protected HOW TO PROTECT YOURSELF If you are beginning to lose confidence in a builder and they have not started the
work, it might be time to take steps to back out of the legally binding devis you have signed. Simply cancelling it requires certain steps to protect yourself. First you must prove that
there is a delay. Where there is a date fixed in the devis for work to start, and an estimate of how long it will take, this is simple. A letter setting out the facts and stating that the
work has not started and so you are cancelling your signature on the devis is enough. Make sure you keep a copy and note whether it was posted or if you hand-delivered it. If you paid a
deposit, you can ask for it back. Hopefully it will arrive without you needing a lawyer to push things along. Where there was no start date on the devis, begin with a telephone call to
ascertain when building might commence. If that is not satisfactory, write a letter, keeping a copy. This can be followed by a formal mise en demeure letter, with signed delivery, requiring
the work to start in eight or 15 days. If no reply is received, send a second, identical letter, again with signed delivery. With no reply to that, you can assume the devis is officially
cancelled, and ask for any deposit back, going to a lawyer if you do not receive a reply. Similarly, if work has started but the builder leaves the site, you need to start gathering proof,
through dated photographs, that the site has been abandoned. You can use these, first by telephone, then with a simple letter and finally by a mise en demeure to end the contract. In this
case you can claim a full refund of any deposit, but be prepared for the builder to contest this as they will argue they have spent money on work already done.
Trending News
Real estate news headlines - 9NewsBuyer coughs up $3.6 million for six car spots in Sydney CBDOne lucky buyer has just spent a jaw-dropping amount of mone...
Vitaminised nanotubes ferry anticancer drugResearchers have synthesized a nanosized drug carrier from multiwalled carbon nanotubes, vitamin E and an organic compou...
Dissolved organic carbon trends resulting from changes in atmospheric deposition chemistryABSTRACT Several hypotheses have been proposed to explain recent, widespread increases in concentrations of dissolved or...
Good Week, Bad Week | The WeekListen in as John Hockenberry and Celeste Headlee, co-hosts of "The Takeaway," bring you an audio version of _...
Holly Barrow | TheArticleFirst {{register.errors.names}} Last Gender What's this for? Age bracket What's this for? This is to help us s...
Latests News
How to deal with builder delays to your property in franceDO YOU RECEIVE THE CONNEXION'S FREE WEEKDAY NEWSLETTER? Sign up here Post-pandemic, it was not uncommon in many par...
Winston churchill and t. E. Lawrence: a brilliant friendship | thearticle_Winston Churchill and T. E. Lawrence walking with Emir Abdullah in the garden of Government House, Jerusalem, during th...
Cryptocurrency news for the week #5_CRYPTOCURRENCY NEWS FOR THE WEEK #5_ In todays blog we are covering this weeks important weekly cryptocurrency and NFT ...
Trademark Films’ David Parfitt Joins London-Based Media Entity Bob & Co As Creative ConsultantLondon-based media banner Bob & Co has brought award-winning producer David Parfitt on-board as a creative consultant. P...
Marco rubio warns syria ‘weeks’ away from ‘collapse and full-scale civil war of epic proportions’Secretary of State Marco Rubio told lawmakers Tuesday that Syria may be weeks away from plunging into another civil war ...